Economics · Financial Management
Arrange the steps followed in evaluating an investment proposal using the Net Present Value (NPV) method in the correct chronological sequence: (A) Calculate the present value of cash flows (B) Identify an appropriate discount rate (C) Forecasting cash flows (D) Rank the projects as per NPV (E) Compute the net present value Choose the correct answer from the options given below:
- 1(D), (A), (C), (B), (E)
- 2(C), (B), (A), (E), (D)✓
- 3(A), (B), (C), (D), (E)
- 4(B), (E), (A), (D), (C)
Correct answer
(C), (B), (A), (E), (D)
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Preparing for Economics?
Practice full-length mock tests with real exam timers, instant score analysis, and all-India ranking.
Want more practice questions on Financial Management?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions
Recommended practice questions in Economics · Financial Management