Arrange the following steps of an engineering survey for highway alignment in the correct chronological order from first to last: I. Preliminary survey II. Reconnaissance survey III. Map study IV. Final location and detailed survey
- 1III, II, I, IV✓
- 2II, III, I, IV
- 3IV, III, I, II
- 4II, III, IV, I
Correct answer
III, II, I, IV