Arrange the following steps of a Budgetary Control system in logical sequence: 1. Creation of Budget Manual 2. Determination of Responsibility for Budgeting 3. Determination of Objectives 4. Determination of Budget Period 5. Organization for Budgeting
- 14, 3, 2, 1, 5
- 25, 4, 3, 2, 1
- 33, 5, 1, 2, 4✓
- 41, 2, 3, 4, 5
Correct answer
3, 5, 1, 2, 4