Arrange the following steps involved in the Critical Path Method (CPM) in the correct sequential order: 1. Determining and defining the essential tasks. 2. Determining the dependency between activities. 3. Computing the time required to complete each activity. 4. Creating a comprehensive list enumerating all activities essential for project completion. 5. Identifying alternative paths.
- 11, 4, 3, 2, 5✓
- 21, 3, 4, 2, 5
- 34, 1, 3, 2, 5
- 43, 4, 1, 2, 5
Correct answer
1, 4, 3, 2, 5
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Preparing for General Studies?
Practice full-length mock tests with real exam timers, instant score analysis, and all-India ranking.
Want more practice questions on Project Management?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions
Recommended practice questions in General Studies · Project Management