Mathematics · Operations Research
Arrange the following steps involved in PERT/CPM in the correct sequence from the first to the last step: I. Computing critical path II. Developing relationship among activities III. Preparation of Work Breakdown Structure IV. Assigning time/cost estimates to activities V. Construction of Network diagram
- 1III, II, V, IV, I✓
- 2I, II, III, IV, V
- 3V, IV, I, III, II
- 4V, IV, III, II, I
Correct answer
III, II, V, IV, I
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Preparing for Mathematics?
Practice full-length mock tests with real exam timers, instant score analysis, and all-India ranking.
Want more practice questions on Operations Research?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions
Recommended practice questions in Mathematics · Operations Research