Arrange the following stages of construction of highway projects in the correct sequence: 1. Clearing site of work or construction 2. Construction of drainage work such as culverts etc. 3. Earthwork 4. Construction of road and its shoulders
- 13, 4, 1, 2
- 22, 1, 4, 3
- 31, 3, 2, 4✓
- 41, 2, 3, 4
Correct answer
1, 3, 2, 4