Arrange the following operations in the correct sequence during cement preparation: (K) Crushing of raw materials (L) Proportioning and blending (M) Burning in kiln (N) Grinding with gypsum (O) Packaging
- 1L → N → K → M → O
- 2K → M → L → N → O
- 3L → K → M → N → O
- 4K → L → M → N → O✓
Correct answer
K → L → M → N → O