Computer · Highway Engineering
Arrange the components of a flexible pavement structure from bottom to top: I. Granular base course II. Bituminous surfacing / binder course III. Granular sub-base layer IV. Prepared soil subgrade
- 1III, II, I, IV
- 2III, II, IV, I
- 3IV, III, II, I
- 4IV, III, I, II✓
Correct answer
IV, III, I, II