Anil and Bablu can do a given piece of work in 50 days, Bablu and Candy can do the same work in 60 days, and Anil, Bablu, and Candy together can complete it in 30 days. Find the number of days required by Bablu alone to finish the total work.
- 1400 days
- 2450 days
- 3550 days
- 4300 days✓
Correct answer
300 days