Mathematics · Project Management Quantitative Methods
An project has activities A(5 days, no predecessor), B(8 days, pred: A), C(7 days, pred: A), D(9 days, pred: C), E(11 days, pred: B,C), F(3 days, pred: E), G(4 days, pred: C), H(3 days, pred: D,G), I(9 days, pred: H,F), and J(7 days, pred: H,I). What is the total project duration determined by the critical path method?
- 128 days
- 239 days
- 332 days
- 443 days✓
Correct answer
43 days
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Preparing for Mathematics?
Practice full-length mock tests with real exam timers, instant score analysis, and all-India ranking.
Want more practice questions on Project Management Quantitative Methods?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions
Recommended practice questions in Mathematics · Project Management Quantitative Methods