An isolated two-phase traffic signal is designed by Webster's method. Determine the optimum signal cycle length if the sum of all critical flow ratios is 0.50 and the all-red time required for pedestrian crossing is 13 seconds.
- 167.5 seconds
- 255 seconds
- 358.5 seconds
- 461 seconds✓
Correct answer
61 seconds