Mathematics · Weighted Average Cost of Capital (WACC)
An infrastructure Special Purpose Vehicle (SPV) is planning to raise ₹800 crore to fund a solar park. The funding plan consists of ₹200 crore in Equity and ₹600 crore in Debt. The Cost of Equity is estimated at 15%. The Debt is raised at an interest rate of 10%. The corporate tax rate is 25%. Calculate the Weighted Average Cost of Capital (WACC) for this project.
- 110.500%
- 28.750%
- 311.250%
- 49.375%✓
Correct answer
9.375%
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Preparing for Mathematics?
Practice full-length mock tests with real exam timers, instant score analysis, and all-India ranking.
Want more practice questions on Weighted Average Cost of Capital (WACC)?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions
Recommended practice questions in Mathematics · Weighted Average Cost of Capital (WACC)