An infrastructure company, Mega-Build Corp, is seeking a Term Loan of 2,000 crore rupees for a highway project under the Hybrid Annuity Model (HAM). The bank is acting as the Lead Bank in a consortium of 5 lenders. The company has a Debt-Equity ratio of 4:1, while the DSCR is projected at a healthy 1.8x. During appraisal, the bank discovers that the company has not yet obtained the Environmental Clearance for a crucial 10 km stretch of the highway. Evaluate the primary Risk and recommended mitigation measure in this scenario.
- 1In a consortium, the Lead Bank's appraisal is final, and environmental clearances are irrelevant to project cash flows.
- 2The lack of environmental clearance creates a Project Execution Risk which can lead to cost overruns; the bank should include a Conditions Precedent clause for disbursement.✓
- 3The DSCR of 1.8x compensates for the high Debt-Equity ratio, and the share pledge mitigates the environmental risk.
- 4The loan should be rejected solely based on the promoter's ED investigation as it violates Know Your Customer (KYC) risk norms.
Correct answer
The lack of environmental clearance creates a Project Execution Risk which can lead to cost overruns; the bank should include a Conditions Precedent clause for disbursement.
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Preparing for General Studies?
Practice full-length mock tests with real exam timers, instant score analysis, and all-India ranking.
Want more practice questions on Credit Risk & Project Appraisal?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions
Recommended practice questions in General Studies · Credit Risk & Project Appraisal