Mathematics · Power Systems
An industrial consumer has a daily load pattern of 2000 kW at 0.8 lagging power factor for 12 hours, and 1000 kW at unity power factor (UPF) for 12 hours. What is the load factor?
- 10.75✓
- 20.50
- 30.60
- 40.65
Correct answer
0.75