General Studies · Project Management
An engineering team faces a tight deadline with a fixed budget. The project schedule would benefit from additional resources, but no extra funds are available. What should the team do?
- 1Prioritize budget allocation to critical tasks only✓
- 2Negotiate with suppliers for discounts or faster deliveries
- 3Invest in faster, high-quality equipment rentals
- 4Reallocate the existing budget to hire temporary labor
Correct answer
Prioritize budget allocation to critical tasks only
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Preparing for General Studies?
Practice full-length mock tests with real exam timers, instant score analysis, and all-India ranking.
Want more practice questions on Project Management?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions
Recommended practice questions in General Studies · Project Management