Aman and Rajan are working at a construction site. Aman can completely build a wall in 15 days, while Rajan takes 20 days to completely demolish it. In how many days will the complete wall be built for the first time if they work on alternate days, with Aman working on the 1st day?
- 1120
- 2117
- 357
- 4113✓
Correct answer
113