After working for 8 days, Payal finds that only 10% of the work is completed. She employs Pinky, who is 50% more efficient than Payal. How many more days will they together take to complete the remaining work?
- 130 days
- 227 days
- 328.8 days✓
- 425 days
Correct answer
28.8 days