Actual production was 1,500 units, completed in 3,620 hours at a variable overhead cost of $11,000. The budgeted standards were 2.5 hours per unit and a variable overhead absorption rate of $3 per hour. Calculate the variable overhead expenditure variance and variable overhead efficiency variance.
- 1Expenditure Variance = $250 Favorable; Efficiency Variance = $300 Adverse
- 2Expenditure Variance = $250 Adverse; Efficiency Variance = $300 Favorable
- 3Expenditure Variance = $140 Favorable; Efficiency Variance = $390 Adverse
- 4Expenditure Variance = $140 Adverse; Efficiency Variance = $390 Favorable✓
Correct answer
Expenditure Variance = $140 Adverse; Efficiency Variance = $390 Favorable
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Preparing for Economics?
Practice full-length mock tests with real exam timers, instant score analysis, and all-India ranking.
Want more practice questions on Cost and Management Accounting?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions
Recommended practice questions in Economics · Cost and Management Accounting