Activities A to K are required to complete a project. The time estimates (in hours) and immediate predecessors are: A(2, -), B(3, -), C(2, -), D(4, A), E(5, B), F(4, B), G(3, C), H(10, D,E), I(5, F), J(8, G), K(3, H,I,J). If the project is completed in the minimum possible time, what is the latest finish time (LFT) for activity G?
- 15 hours
- 210 hours✓
- 38 hours
- 49 hours
Correct answer
10 hours
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Preparing for Mathematics?
Practice full-length mock tests with real exam timers, instant score analysis, and all-India ranking.
Want more practice questions on Industrial Engineering & Operations Research?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions
Recommended practice questions in Mathematics · Industrial Engineering & Operations Research