According to which project management technique is any given activity delineated in a network treated probabilistically, implying it is unlikely to be completed exactly on a single deterministic time?
- 1Bar Chart
- 2Gantt Chart
- 3Critical Path Method (CPM)
- 4Program Evaluation and Review Technique (PERT)✓
Correct answer
Program Evaluation and Review Technique (PERT)