According to standard public works department guidelines, a revised estimate must be prepared when the actual expenditure of a work exceeds or is likely to exceed the original administrative approval by more than what fraction?
- 10.05 (5%)✓
- 20.3 (30%)
- 30.4 (40%)
- 40.5 (50%)
Correct answer
0.05 (5%)