According to standard concrete practice guidelines, reinforcing bars shall NOT be lapped unless the length required exceeds:
- 1The minimum structural development length
- 2The maximum commercial or available length of the bar✓
- 3The standard anchorage length requirement
- 4The clear span length of the structural member
Correct answer
The maximum commercial or available length of the bar