According to Putnam's Software Lifecycle Management (SLIM) model, project effort is inversely proportional to the fourth power of development time. If the development schedule for a 100 Person-Month (PM) project is doubled, what will the required project effort be reduced to?
- 16.25 PM✓
- 212.5 PM
- 325 PM
- 450 PM
Correct answer
6.25 PM