Computer · Building Construction & Standards
According to IS 10440, the formwork for Reinforced Brick (RB) and Reinforced Brick Concrete (RBC) floors or roofs should not be removed before how many days after laying?
Verified Solution4 OptionsUpdated: October 2026👁️1 View
Share:
- 121 days
- 214 days✓
- 310 days
- 47 days
Correct answer
14 days
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
👥
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Online Test Series
Preparing for Computer?
Practice full-length Computer mock tests with real exam timers, instant score analysis, and all-India ranking.
Chapter Practice
Practice Building Construction & Standards MCQs →Want more practice questions on Building Construction & Standards?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions
Recommended practice questions in Computer · Building Construction & Standards