According to Indian standards, which type of formwork requires a maximum stripping time of 14 days?
- 1Soffit formwork to beams
- 2Soffit formwork to slabs
- 3Props to slabs spanning over 4.5 m
- 4Props to beams spanning over 6 m✓
Correct answer
Props to beams spanning over 6 m