Computer · Estimating, Costing and Valuation
According to central public works guidelines, a revised estimate is prepared when the original sanctioned estimate exceeds by more than what percentage due to a change in price levels?
- 13%
- 25%✓
- 38%
- 410%
Correct answer
5%