Above what approximate break-even distance for an overhead transmission line does the total cost of an HVDC system become lesser than an HVAC system?
- 1Less than 10 km
- 2Greater than 100 km and less than 300 km
- 3Greater than 600 km✓
- 4Less than 50 km
Correct answer
Greater than 600 km