A work can be completed in 10 days if X, Y, and Z work together. All three started working together. X left after 4 days, and then Y and Z completed the remaining work in 10 more days. In how many days could X alone complete the entire work?
- 115 days
- 225 days✓
- 330 days
- 435 days
Correct answer
25 days