Mathematics · Mensuration
A trapezoidal canal with a bottom width of 6 m, a depth of 2 m, having a side slope of 2:1 (Horizontal:Vertical) is formed in cutting for a length of 1 km. The volume of earthwork to be excavated is:
- 120000 m3✓
- 228000 m3
- 316000 m3
- 414600 m3
Correct answer
20000 m3