Mathematics · Work and Time
A team of 91 workers, all working at the same speed, was deployed to construct a structure. Starting from the second day, 13 workers left at the beginning of each day, and this pattern continued until the work was completed. Find the number of days it would have taken to complete the structure if all 91 workers had worked together for all the days.
- 14 days✓
- 25 days
- 33 days
- 42 days
Correct answer
4 days