A team of 7 software developers can complete a mobile app project in 12 days. They begin working on it, but after 5 days, 2 developers are reassigned to another task. How many more days will the remaining developers take to finish the project?
- 17 days
- 210 days
- 38 days
- 49.8 days✓
Correct answer
9.8 days