Electrical Engineering · Power Electronics
A step-up chopper is used to deliver a load voltage of 500 V from a 220 V d.c. source. If the blocking period (off-time) of the thyristor is 80 μs, the required pulse width (on-time) is:
- 1152.4 μs
- 292.4 μs
- 3101.8 μs✓
- 450.8 μs
Correct answer
101.8 μs