A step-up chopper is used to deliver a load voltage of 400 V from a 200 V D.C. source. If the blocking period (off-time) of the thyristor is 80 μs, compute the required pulse width (on-time).
- 1200 μs
- 2500 μs
- 3160 μs
- 480 μs✓
Correct answer
80 μs