Mathematics · Time and Work
A started a work and left after working for 9 days, then B finished the remaining work in 24 days. Had A left the work after working for 13 days, B would have finished the remaining work in the next 18 days. In how many days can A and B together complete the work?
- 112 days
- 215 days✓
- 316 days
- 418 days
Correct answer
15 days