A scheduled activity may begin 10 days before its predecessor activity finishes. This relationship is an example of a lead in which dependency type?
- 1Finish to Start✓
- 2Finish to Finish
- 3Start to Finish
- 4Start to Start
Correct answer
Finish to Start