A revised estimate is prepared in central/state public works departments primarily when:
- 1there is a minor material deviation of structured nature
- 2the sanctioned estimate is likely to exceed by more than 5% with important structural alterations
- 3the expenditure of the work exceeds 20% of the administrative approval
- 4the sanctioned estimate is likely to exceed by more than 5% or expenditure exceeds sanctioned funds by 10%, due to increase in rates or cost of materials without structural alteration✓
Correct answer
the sanctioned estimate is likely to exceed by more than 5% or expenditure exceeds sanctioned funds by 10%, due to increase in rates or cost of materials without structural alteration
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Preparing for Computer?
Practice full-length mock tests with real exam timers, instant score analysis, and all-India ranking.
Want more practice questions on Estimation and Costing?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions
Recommended practice questions in Computer · Estimation and Costing