General Studies · Industrial Engineering and Operations Research
A refining unit's pump has the following data for a month: - Total Operating Time available: 720 hours - Breakdown Time: 20 hours - Minor Stoppage Time: 10 hours - Actual Operating Speed: 80% of Ideal Speed - Defective Output (Quality Loss): 10% of Total Output Calculate the pump's Availability Rate, Performance Rate, and Overall Equipment Effectiveness (OEE) using standard TPM principles.
- 1Availability Rate: 97.00%; Performance Rate: 75.00%; OEE: 65.00%
- 2Availability Rate: 96.00%; Performance Rate: 90.00%; OEE: 69.00%
- 3Availability Rate: 96.25%; Performance Rate: 80.00%; OEE: 67.76%
- 4Availability Rate: 95.83%; Performance Rate: 80.00%; OEE: 69.00%✓
Correct answer
Availability Rate: 95.83%; Performance Rate: 80.00%; OEE: 69.00%
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Preparing for General Studies?
Practice full-length mock tests with real exam timers, instant score analysis, and all-India ranking.
Want more practice questions on Industrial Engineering and Operations Research?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions
Recommended practice questions in General Studies · Industrial Engineering and Operations Research