Mathematics · Financial Management
A project manager is considering two mutually exclusive investment proposals. Proposal X requires an initial outlay of 8,00,000 and is expected to generate net cash inflows of 2,50,000 per annum for 5 years. Proposal Y requires an initial outlay of 1,00,000 and is expected to generate 3,20,000 per annum for 5 years. The cost of capital is 12%. Which of the following is correct regarding the Net Present Value (NPV) of these projects? (Use the 5-year annuity factor at 12%: 3.6048).
- 1Proposal Y is better because its NPV is 1,12,500.
- 2Proposal X has a higher Profitability Index than Proposal Y.
- 3Proposal Y is better because its NPV is 1,53,536.✓
- 4Proposal X is better because its NPV is 1,01,200.
Correct answer
Proposal Y is better because its NPV is 1,53,536.
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Preparing for Mathematics?
Practice full-length Mathematics mock tests with real exam timers, instant score analysis, and all-India ranking.
Want more practice questions on Financial Management?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions
Recommended practice questions in Mathematics · Financial Management