Mathematics · Project Management
A project consists of seven activities as shown below. Find the total project duration: Activity | Time (weeks) | Predecessor P | 7 | - Q | 4 | - R | 2 | Q S | 11 | P T | 9 | P, R U | 9 | Q V | 4 | T, U
- 117 weeks
- 218 weeks
- 320 weeks✓
- 419 weeks
Correct answer
20 weeks
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Preparing for Mathematics?
Practice full-length mock tests with real exam timers, instant score analysis, and all-India ranking.
Want more practice questions on Project Management?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions
Recommended practice questions in Mathematics · Project Management