A production plant has the following process hours available for three sequential operations: - Weighing and Chopping: 2 hours - Mixing and Finishing: 5 hours - Baking: 24 hours Which of these activities represents the bottleneck process?
- 1Weighing and Chopping✓
- 2Mixing and Finishing
- 3Baking
- 4There is no bottleneck
Correct answer
Weighing and Chopping