A production line budgeted for 2,000 standard labor hours at $10 per hour. Due to inefficiency, the workers took 2,200 actual hours and were paid $11 per hour. What was the total direct labour variance?
- 1Nil
- 2$22,000 Favourable
- 3$20,000 Adverse✓
- 4$6,000 Favourable
Correct answer
$20,000 Adverse