Mathematics · Power Plant Economics
A power station has a maximum demand of 15,000 kW. The annual load factor is 50% and the plant capacity factor is 40%. What is the plant capacity?
- 115,250 kW
- 218,750 kW✓
- 317,500 kW
- 430,000 kW
Correct answer
18,750 kW