Mathematics · Power Systems
A power plant has an installed capacity of 150 MW. If its plant capacity factor is 60% and its load factor is 80%, determine the maximum demand on the plant.
- 1470.5 MW
- 2385.5 MW
- 3274.5 MW
- 4112.5 MW✓
Correct answer
112.5 MW