Mathematics · Time and Work
A piece of work can be completed in 10 days if x, y, and z work together. All three started working together. x left after 4 days, and then y and z completed the remaining work in 10 more days. In how many days can x alone complete the entire work?
- 128 days
- 230 days
- 335 days
- 425 days✓
Correct answer
25 days