Mathematics · Time and Work
A piece of work can be completed by P and Q together in 24 days, and the same piece of work can be completed by R alone in 60 days. If P and R together can do the same work in 36 days, then find the time taken by Q to complete this piece of work al one.
- 132811 days✓
- 2367 days
- 329913 days
- 4845 days
Correct answer
32811 days
Download Single Question PDF