A PERT network has three activities on the critical path with mean times of 3, 8, and 6 days, and standard deviations of 1, 2, and 3 days respectively. The probability that the project will be completed in 20 days is approximately:
- 10.95
- 20.84✓
- 30.66
- 40.50
Correct answer
0.84