A nuclear power plant generates 800 MWh of energy per day while operating at a load factor of 85%. What is the maximum demand on the power plant?
- 119.45 MW
- 239.22 MW✓
- 357.80 MW
- 482.73 MW
Correct answer
39.22 MW