A manufacturing company uses three processes to make its two products, X and Y. The table below details the process times per product and daily capacity limitations: Process 1: 22 Hours available per day | 1.00 Hr required for X | 0.75 Hr required for Y Process 2: 22 Hours available per day | 0.75 Hr required for X | 1.00 Hr required for Y Process 3: 18 Hours available per day | 1.00 Hr required for X | 0.50 Hr required for Y Daily demand for product X and product Y is 10 units and 16 units respectively. Which of the following will successfully improve total throughput?
- 1Reducing the time product X requires for Process 1
- 2Reducing the time taken for rest breaks on Process 3
- 3Increasing the external market demand for both products
- 4Increasing the efficiency of the maintenance routine to release capacity on Process 2✓
Correct answer
Increasing the efficiency of the maintenance routine to release capacity on Process 2
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Preparing for Mathematics?
Practice full-length mock tests with real exam timers, instant score analysis, and all-India ranking.
Want more practice questions on Linear Programming and Operations Management?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions
Recommended practice questions in Mathematics · Linear Programming and Operations Management