General Studies · Project Management
A manager has prepared a Detailed Project Report (DPR) for an upcoming venture. Which of the following is typically NOT considered an inherent element of a standard DPR?
- 1Strategy to be followed
- 2Delegation of individual daily tasks✓
- 3Expected budget for expenses
- 4Objectives to be achieved
Correct answer
Delegation of individual daily tasks