A levelling work was carried out along a falling gradient using a dumpy level and a levelling staff of 4 m length. The following successive five readings were taken: 1.455 m, 2.36 m, 0.59 m, 1.78 m, and 1.12 m. The level was shifted to a new set up after the second reading. What is the correct order of booking the readings in the field book? (BS - Back sight, FS - Fore sight, IS - Intermediate sight)
- 1BS, FS, IS, BS, FS
- 2BS, FS, BS, IS, FS✓
- 3BS, FS, BS, IS, IS
- 4BS, IS, BS, FS, FS
Correct answer
BS, FS, BS, IS, FS
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Preparing for Computer?
Practice full-length mock tests with real exam timers, instant score analysis, and all-India ranking.
Want more practice questions on Surveying?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions
Recommended practice questions in Computer · Surveying